Keeping a Pre-Offer Repair Estimate Honest
A repair estimate written before an offer is a forecast made with partial information. It will be wrong; the aim is to be wrong by an amount the deal can absorb. These practices come from the arithmetic of how estimates fail.
Do
- Write the scope before attaching prices. List what will be done room by room first. Pricing a vague scope just produces a precise-looking vague number.
- Separate the big systems. Roof, foundation, electrical service, plumbing supply and drains, and heating and cooling each get their own line, because each can swing the total by itself.
- Carry an explicit contingency line. Hidden damage behind walls and under floors is normal in older houses; a named contingency keeps that risk visible rather than buried in rounded-up line items.
- Note what you could not see. An unreachable attic or a locked room is an unknown, and unknowns deserve their own allowance.
- Price with the end buyer's costs in mind. The buyer, not you, will pay for the work, so the estimate should reflect a contractor's price, not your own labour.
Don't
- Don't price the whole house per square foot. That shortcut hides the two or three items that dominate the total, such as a foundation repair, which do not scale with floor area.
- Don't double-count. Painting can appear under each room and again under "interior paint". Pick one place.
- Don't let the target MAO set the budget. Reverse-engineering repairs to make a number work is the most common source of later disputes.
- Don't forget permits. Many Texas cities require permits for electrical, plumbing, mechanical and structural work, and the fee and inspection time belong in the plan.
A hypothetical estimate layout
Illustrative round numbers only; real prices vary by region, house and contractor.
| Line | Hypothetical amount | Confidence |
|---|---|---|
| Roof replacement | 12,000 | Medium: no attic access |
| Kitchen | 18,000 | High: scope clear |
| Bathrooms (two) | 14,000 | High |
| Flooring and paint | 11,000 | High |
| HVAC replacement | 8,000 | Low: unit age unknown |
| Permits | 1,500 | Medium |
| Contingency | 9,000 | Covers low-confidence lines |
| Total | 73,500 |
The confidence column is the most useful habit on this page: it tells you which lines to verify with a contractor bid before signing anything. For a room-by-room walkthrough, see the repair scope checklist.
Why contingency is a percentage of the risky lines, not the total
Many estimators add a flat share of the whole budget as contingency. A more careful approach sizes it from the low-confidence lines. If the kitchen and flooring are clearly scoped but the roof, HVAC and foundation are unknown, the uncertainty sits almost entirely in those three, so the allowance should be large relative to them and small relative to the cosmetic work. That approach also tells you what to verify first: a contractor's look at the three uncertain systems can shrink the contingency more than any amount of re-pricing paint and trim.
When to get a bid before the offer
A bid costs time and goodwill, so save it for lines that could change the decision. A hypothetical test: if moving one line from its low estimate to its high estimate would push the offer below what the owner will accept, that line deserves a professional opinion before you sign.
This page teaches estimating habits in general terms. It is not a construction bid, and structural or safety questions should go to a licensed professional.