How to Turn a Repair Estimate Into a Draw Schedule
Repair money is rarely spent all at once. Lenders who fund renovation commonly release it in draws after work is checked, and even cash buyers pay contractors in stages. Building a draw schedule turns a repair total into a timeline, which improves the interest estimate and shows how much cash the buyer needs at the peak.
What you need
- The line-item repair estimate.
- A rough sequence of work: demolition and rough-in first, finishes later.
- The buyer's financing terms, or reasonable placeholders.
- A spreadsheet with one column per month.
Steps
- Group lines into phases. For example: phase 1, demolition, roof and structural; phase 2, rough plumbing, electrical and HVAC; phase 3, drywall, cabinets and flooring; phase 4, paint, fixtures and punch list.
- Assign months. Place each phase in the month it is expected to be paid for, usually after completion and inspection.
- Note any deposit. Some contractors ask for a deposit at the start; put it in month zero or one.
- Add permit timing. Permits must be issued before regulated work starts.
- Compute cumulative repair spend by month.
- Calculate interest on drawn funds. If the loan charges interest only on what has been drawn, each month's interest is the rate times the balance outstanding.
- Add the purchase loan and carry. Combine with the purchase loan balance and monthly carrying costs to see total cash out by month.
- Mark the peak. The highest point of cumulative cash invested is what the buyer must be able to fund.
A hypothetical schedule
Repair estimate 60,000, purchase loan 130,000, illustrative 12 percent annual interest charged only on drawn funds.
| Month | Phase paid | Draw | Repair balance drawn | Interest on purchase loan | Interest on repair balance |
|---|---|---|---|---|---|
| 1 | Deposit and phase 1 | 15,000 | 15,000 | 1,300 | 150 |
| 2 | Phase 2 | 15,000 | 30,000 | 1,300 | 300 |
| 3 | Phase 3 | 20,000 | 50,000 | 1,300 | 500 |
| 4 | Phase 4 | 10,000 | 60,000 | 1,300 | 600 |
| 5 | Listing | 0 | 60,000 | 1,300 | 600 |
| 6 | Sale closes | 0 | 60,000 | 1,300 | 600 |
| Total | 60,000 | 7,800 | 2,750 |
Interest on the repair portion totals 2,750 here, compared with 3,600 if the full 60,000 had been charged interest from month one. The 850 difference is small on this invented deal but grows with larger budgets and longer schedules.
Common mistakes
- Charging interest on the whole repair budget from day one when the loan does not.
- Assuming draws are released instantly; inspections and paperwork take days.
- Forgetting that the buyer usually funds work before reimbursement under some loans.
- Leaving permits and contractor lead time off the schedule.
Where the result goes
The interest figure replaces the rough interest line in holding costs, and the peak cash need goes in the notes for any end buyer reviewing the deal. The cost timeline diagrams show the same idea as a curve.