Deal Math 4: Building the Holding Line
Time costs money even when nothing happens. Part 4 builds House 1's holding line: how long the end buyer will own the house and what each month costs, excluding financing, which is Part 5.
Step 1: Build the hold from parts
| Part | Basis | Weeks |
|---|---|---|
| Close the purchase | Contract terms | 2 |
| Contractor start | Written start date | 3 |
| Work | Scope from Part 3 | 9 |
| Punch list | Experience | 1 |
| On market | Agent's local days on market | 5 |
| Close the resale | Typical closing time | 4 |
| Total | 24 weeks, about 5.5 months; use 6 |
Rounding up reflects the fact that most parts can slip and few finish early.
Step 2: Monthly carrying costs
| Line | Basis | Per month |
|---|---|---|
| Property tax | Estimate without the seller's homestead exemption | 550 |
| Insurance | Written quote for a vacant or renovation policy | 300 |
| Utilities and lawn | Recent bills | 200 |
| HOA dues | Association statement | 0 for House 1 |
| Total | 1,050 |
Holding line: 6 months x 1,050 = 6,300. House 1's sheet rounds the line, with small items such as security and lock changes, to 9,000 including a modest allowance for a slower sale.
Texas points to watch
- Property tax. Often the largest carrying cost. Remove the seller's exemptions and check special district taxes.
- January 1. If the hold crosses it, the next year's valuation may rise once the work is visible.
- Insurance. Quote every deal; older roofs and coastal locations change everything.
Common mistakes
- Using the seller's exempt tax bill
- A template insurance figure
- A hold assumed rather than built
The holding line on House 1's sheet
"Holding 9,000: six-month hold built from parts (contractor start date in writing; agent's days on market); non-homestead tax estimate; quoted insurance; utilities."
How holding affects later parts
Financing in Part 5 runs for the same months. A one-month error in the hold therefore moves two lines.
Checking each part of the hold
Each part of the hold can be checked by someone: the contract states the purchase closing period; the contractor's written start date covers the wait; the scope and the contractor's schedule cover the work; the agent's data covers days on market; the title company can say how long resale closings are taking. When an end buyer challenges the hold, the answer is a list of sources rather than an opinion. If any part depends on a permit, add the city's typical review time.
Seasonal effects
If House 1's resale would fall in a quieter season, ask the agent for days on market observed in the same months of recent years and adjust that part rather than the whole hold.
Continue to Deal Math 5. Figures are hypothetical; WholeSellTX offers this as general education.