Hypothetical Deal 2: Pricing a Foundation Unknown, Then Re-Pricing
All figures are invented and rounded for teaching. House B is fictional.
The house
An older single-family house on expansive clay soil, common in parts of Texas. Diagonal cracks above two doors, a sticking back door and a slight slope in one room. Otherwise sound, with a newer roof.
Step 1: The unknown
Without an engineer's evaluation, the foundation could need anything from minor work to extensive repair. Guessing the worst kills the deal; guessing the best risks the end buyer's money.
Step 2: An expected-value allowance (before the report)
The analyst lists outcomes, a rough probability for each based on judgement, and a cost.
| Outcome | Judged probability | Cost | Probability x cost |
|---|---|---|---|
| Minor: monitoring and drainage | 0.4 | 3,000 | 1,200 |
| Moderate: partial piering | 0.4 | 12,000 | 4,800 |
| Major: extensive piering and repairs | 0.2 | 30,000 | 6,000 |
| Expected allowance | 12,000 |
The probabilities are labelled as judgement. The analyst adds a note that the worst case is 30,000.
Step 3: First MAO
| Line | Amount |
|---|---|
| ARV | 260,000 |
| Repairs excluding foundation | 38,000 |
| Foundation allowance | 12,000 |
| Holding, selling and closing | 32,000 |
| End buyer margin | 28,000 |
| Fee | 7,000 |
| MAO | 143,000 |
Step 4: The engineer's report
A licensed professional engineer evaluates the foundation and recommends partial piering and drainage correction. A foundation company bids 14,000 with a transferable warranty.
Step 5: Re-priced MAO
Replacing the 12,000 allowance with the 14,000 bid lowers MAO by 2,000, to 141,000. Uncertainty has been replaced by a known cost, which is worth more to an end buyer than the small change in price.
What the case shows
- An expected-value allowance is a reasoned placeholder, not a forecast.
- Showing the worst case alongside it is honest.
- A report converts risk into cost and narrows negotiations.
What could have gone differently
Had the report recommended extensive work, MAO would have fallen by 18,000 from the first figure. Some end buyers would walk; others would price it.
How to choose the probabilities
The probabilities in Step 2 are not data; they are the analyst's judgement, informed by the visible signs, the house's age and soil type, and past files. Writing them down has two benefits. First, it makes the judgement visible to an end buyer, who can disagree with a specific number rather than with the whole offer. Second, it lets the analyst compare judgements with outcomes later, in the kind of forecast log described in the benchmarking page. Over time, an analyst who records probabilities and outcomes learns whether they are habitually optimistic or pessimistic about foundations.
What the end buyer sees
The deal sheet shows the allowance, the worst case and, once available, the engineer's report and bid. An end buyer who sees all three can price their own risk. A deal sheet that shows only a single unexplained foundation figure invites either suspicion or an even larger allowance from the buyer, both of which cost the seller.
WholeSellTX offers this hypothetical as general education. For structural questions, consult a licensed professional engineer; see the trade credentials page.