Debate: A Flat Contingency Percentage or One Sized by Line?
Every repair estimate needs a contingency. The debate is how to size it: a flat percentage of the total, or line by line according to how confident you are in each figure.
The case for a flat percentage
- Simple and fast. One number, applied consistently.
- Easy to explain. End buyers recognise it.
- Hard to game. You cannot quietly shrink it on the lines you like.
The case for line confidence
- Risk is not spread evenly. A painted wall is predictable; a 1960s drain line is not.
- Better totals. Applying a high allowance to uncertain lines and a low one to certain lines produces a contingency that reflects the actual house.
- Better learning. You can compare outcomes by line and recalibrate.
A hypothetical comparison
| Line | Estimate | Confidence | Line allowance |
|---|---|---|---|
| Paint | 6,000 | High | 300 |
| Flooring | 9,000 | High | 450 |
| Kitchen | 15,000 | Medium | 1,500 |
| Sewer line | 5,000 | Low | 2,500 |
| Electrical | 4,000 | Low | 2,000 |
| Total | 39,000 | 6,750 |
A flat 10 percent would give 3,900. The line method gives 6,750 because two uncertain lines carry most of the risk. On a different house with only cosmetic work, the line method would give less than 10 percent.
Where each goes wrong
- Flat percentages under-cover risky houses and over-cover simple ones.
- Line confidence can drift toward optimism if the analyst rates everything "high".
A practical compromise
Use line confidence, but set a floor, for example a minimum overall contingency, and review the confidence ratings against past outcomes each quarter.
Questions that decide it
- How varied is the risk across lines?
- Do you have past files to calibrate confidence?
- Will the end buyer accept the method?
Calibrating confidence ratings
Confidence ratings are only useful if they mean something. After each project, compare each line's final cost with its estimate and note the rating you gave it. If "high confidence" lines regularly miss by large amounts, your ratings are optimistic and the allowances should rise. If "low confidence" lines regularly come in on budget, you may be over-cautious. A simple table of rating, estimate and outcome, kept across projects, turns gut feeling into evidence within a year.
Explaining it to an end buyer
Show the line allowances in a column next to the estimates. A buyer can see at a glance where you think the risk is and can disagree line by line. That conversation is more productive than arguing over a single total percentage.
WholeSellTX presents both views for general education. See sizing contingency from line confidence; figures are hypothetical.