How to Size a Contingency From the Confidence of Each Line
A flat contingency, applied the same way to every house, ignores the fact that some estimates are far less certain than others. This how-to gives a repeatable way to size contingency from the estimate itself. It adds about ten minutes to a repair estimate and produces a number you can explain.
What you need
- A line-item repair estimate, with a scope for each line.
- Your notes from the walk-through, including anything you could not see.
- A spreadsheet.
Steps
- Rate each line. Give every line a confidence rating: high (scope clear, price from a bid or close reference), medium (scope clear, price estimated), or low (scope uncertain, or the item could not be inspected).
- Give each rating a range. Decide how far above the estimate a line could plausibly land. For teaching, use hypothetical ranges: high plus 5 percent, medium plus 15 percent, low plus 40 percent. Choose your own from experience.
- Compute each line's upside. Multiply the line amount by its range.
- Do not simply add the upsides. Not every line will go wrong at once. A common simplification is to take a share of the summed upside; another is to take the largest single upside plus a share of the rest. Pick one method and use it every time.
- Write the contingency as its own line, with a note on the method.
- Revisit after verification. When a bid or inspection turns a low-confidence line into a high-confidence one, re-run the calculation and the contingency will shrink.
A hypothetical worked example
| Line | Amount | Confidence | Range | Upside |
|---|---|---|---|---|
| Kitchen | 16,000 | High | 0.05 | 800 |
| Baths | 12,000 | High | 0.05 | 600 |
| Flooring and paint | 10,000 | High | 0.05 | 500 |
| HVAC | 7,500 | Medium | 0.15 | 1,125 |
| Roof | 11,000 | Low | 0.40 | 4,400 |
| Foundation allowance | 5,000 | Low | 0.40 | 2,000 |
| Total | 61,500 | 9,425 |
Method chosen: largest single upside plus half of the rest. Contingency = 4,400 + 0.5 × 5,025, about 6,900, or roughly 11 percent of the estimate. A different house with all lines rated high would get far less; one with several uninspected systems would get more.
After a roof bid
Suppose a roofer bids 10,500 for the roof, so the line becomes high confidence with an upside of about 525. The largest upside is now the foundation's 2,000; contingency becomes 2,000 + 0.5 × 3,550, about 3,800. The bid cut contingency by about 3,100, which is often worth more than the bid itself costs in time.
Why not just use a flat share?
A flat share is easy to explain and hard to argue with, which is exactly its weakness. On a house where everything was visible and priced from bids, it overcharges the buyer for risk that is not there and lowers the offer more than necessary. On a house with an uninspected roof and an unknown sewer line, it undercharges and leaves the deal exposed. Tying contingency to the confidence of each line makes the number move for the right reasons, and it gives you something specific to say when an end buyer asks why the allowance is the size it is.
Common mistakes
- A flat percentage regardless of what was inspected.
- Hiding contingency inside inflated line items.
- Never shrinking contingency after verification.
- Treating contingency as profit the buyer can count on.
See the repair practices page for related estimating habits.
The ranges above are invented teaching values. This is general education on estimating method, not a construction bid.