Masterclass: Pricing a Repair You Cannot Yet Confirm
Some repairs are a coin toss before an offer. A slab on expansive clay might need nothing more than monitoring, or it might need a substantial repair; a sewer line might be fine or might need replacing. This lesson shows how to price that kind of uncertainty with an expected-value allowance, and why the allowance alone is not enough. All numbers are invented.
Part 1: Expected value in one line
An expected-value allowance multiplies each possible outcome by your estimate of its likelihood and adds them up:
Allowance = sum of (probability of outcome × cost of outcome)
It is the average cost you would expect across many similar houses. It is not what this house will cost.
Part 2: A foundation example
A hypothetical slab house shows a few brick cracks and one sticking door, typical of movement on clay soils in parts of Texas. Before an engineer's evaluation, the analyst sketches three outcomes:
| Outcome | Likelihood (judgement) | Cost (hypothetical) | Weighted |
|---|---|---|---|
| Minor: monitoring and drainage correction | 0.5 | 2,000 | 1,000 |
| Moderate: partial pier repair | 0.35 | 9,000 | 3,150 |
| Major: extensive repair | 0.15 | 22,000 | 3,300 |
| Expected-value allowance | 1.0 | 7,450 |
The likelihoods are judgements, and that should be stated. They should come from what you have seen, what local contractors and engineers say about similar houses, and the visible evidence on this one.
Part 3: Why the allowance is not the whole answer
If the major outcome happens, the actual cost is 22,000, nearly three times the allowance. A single deal does not average out. So underwriting needs two numbers:
- The allowance in the base case, because it is the best single estimate.
- The bad outcome in the stress case, because it tells you whether the deal survives if the worst plausible outcome arrives.
Using the invented figures, the base-case offer includes 7,450 for the foundation and the stress case includes 22,000. If the deal fails in the stress case, the decision is whether to get an engineer's evaluation before signing, or to price for the worst case.
Part 4: The value of information
An engineer's evaluation costs money and time. It is worth buying when it could change the decision. A quick test: if the stress-case offer is below what the owner will accept but the base case is above it, the evaluation decides the deal, so it is probably worth getting. If both cases work, or both fail, the evaluation will not change your answer.
Part 5: Applying the same method elsewhere
| Uncertain item | Typical outcomes to sketch |
|---|---|
| Sewer line under slab | No issue; spot repair; full replacement |
| Roof with no attic access | Repair; overlay not possible so full tear-off; decking replacement as well |
| HVAC of unknown age | Service only; component repair; full replacement |
| Hidden water damage | None; local subfloor; widespread |
Part 6: Common mistakes
- Using only the allowance and ignoring the bad outcome.
- Presenting judgement probabilities as if they were measured.
- Counting the same risk twice, once as an allowance and again inside general contingency.
- Not updating once an inspection or bid resolves the uncertainty.
Exercise
For a hypothetical roof with no attic access on a 1990s house, sketch three outcomes with likelihoods and costs, compute the allowance, and state the stress-case figure.
For who can evaluate foundations and other systems, see the trade credentials page; for contingency, the contingency how-to.
This lesson is general education with invented probabilities and costs. Foundation and structural questions require a licensed professional engineer.