Copyable Template: Scope of Work for a Bid Request
A contractor can only price what you describe. This template turns your walk-through notes into a scope of work clear enough for a pre-offer bid, so the numbers that come back can drop straight into the repair estimate. Fill in the brackets and delete lines that do not apply. An invented example follows.
The template
Bid request: [area, not the owner's name]
Date: [date] · Access arranged: [date and time window] · Bid needed by: [date]
Property facts
- Single-storey / two-storey, [living area] sq ft, built [year]
- Foundation type: [slab / pier and beam / unknown]
- Occupied or vacant: [ ]
Purpose
Pre-purchase estimate for a resale-standard renovation. Please price each line separately.
Line items
| # | Area | Work requested | Quantity | Finish level |
|---|---|---|---|---|
| 1 | [ ] | [ ] | [ ] | [ ] |
| 2 | [ ] | [ ] | [ ] | [ ] |
Items to evaluate rather than price
- [e.g. roof decking condition, HVAC condition, visible foundation movement]
Exclusions
- [e.g. appliances supplied by owner, landscaping]
Permits and licensing
- Please state which lines require permits and include fees.
- Please confirm licences for regulated trades (electrical and air conditioning work is licensed through TDLR in Texas).
Bid format requested
- Price per line, with material and labour combined
- Lead time to start and expected duration
- Payment schedule
- What would change the price once work begins
Invented example (excerpt)
| # | Area | Work requested | Quantity | Finish level |
|---|---|---|---|---|
| 1 | Kitchen | Remove and replace base and wall cabinets | 22 lin ft | Stock, shaker style |
| 2 | Kitchen | Install counters | 44 sq ft | Mid-range stone |
| 3 | Baths (2) | Replace vanity, toilet, fixtures; reglaze tub | 2 | Builder grade |
| 4 | Whole house | LVP flooring excluding baths | 1,300 sq ft | Mid-range |
| 5 | Roof | Evaluate; price tear-off and replacement if needed | approx. 17 squares | Architectural shingle |
Why each section is there
- Quantities stop contractors guessing and make bids comparable.
- Finish level prevents one bid pricing builder grade and another premium.
- Evaluate rather than price gets an opinion on uncertain systems without forcing an inflated number.
- Lead time and duration feed the holding period directly.
- Price-change conditions tell you where contingency still belongs.
After the bids arrive
Enter each line price beside your estimate. Where bids differ widely on one line, the scope may be unclear; clarify and re-ask. Update your price list with the new data points.
Courtesy
Contractors spend unpaid time on pre-offer bids. Be clear that the bid is for a property you do not yet own, respect their time, and share the outcome.
Comparing bids fairly
When two or three bids come back, line them up row by row before looking at totals. A low total often hides an excluded item or a lower finish level, and a high total may include work the others left out. Where a line differs widely, ask each contractor what they assumed; the answer often reveals something about the house that you missed on the walk-through. Record both the price and the contractor's assumption beside each line, because next time the assumption may matter more than the number.
This template is a general learning resource. A bid is the contractor's offer, not this site's estimate, and regulated work must be done by appropriately licensed trades.