How to Review a Contractor Bid Before It Goes Into the Model
A contractor bid often replaces your own estimate in the model. Before it does, check that it prices what you think it prices. This method lists criteria; it does not rate contractors.
The criteria
| Criterion | What to check |
|---|---|
| Scope match | Every line in your scope appears, with quantities |
| Exclusions | What is explicitly not included |
| Allowances | Items priced as allowances (for example fixtures) and their amounts |
| Permits | Who pulls permits and whether fees are included |
| Schedule | Start date, duration and what happens if delayed |
| Payment terms | Deposit, draws and holdback |
| Change orders | How extra work is priced |
| Credentials and insurance | Licences for regulated trades, proof of insurance |
| Warranty | What is covered and for how long |
Exclusions are where estimates fail
A low bid that excludes demolition, disposal, permits or drywall repair after plumbing work is not low. Add the excluded items at your own estimate to compare bids fairly.
Allowances
An allowance for fixtures or tile is a placeholder. If your finish level is higher, the bid will rise. Set allowances to match the finish level the ARV assumes.
Schedule as a cost
A bid that starts in six weeks adds six weeks of holding cost. Convert it to money and add it to the bid when comparing.
Regulated trades
In Texas, electricians and plumbers are licensed by state bodies, and some HVAC work requires licensing. Check the relevant licence for those trades.
A hypothetical comparison
| Item | Bid A | Bid B |
|---|---|---|
| Base price | 38,000 | 43,000 |
| Excluded items at your estimate | +4,500 | 0 |
| Start delay cost | +2,700 | 0 |
| Comparable total | 45,200 | 43,000 |
The apparently cheaper bid is more expensive once exclusions and delay are counted. Figures are hypothetical.
Putting it in the model
Use the comparable total, keep the contingency for unknowns, and record the bid date.
Payment terms and risk
A large upfront deposit increases risk if the contractor fails to start or finish. Draws tied to completed stages, with a holdback until final inspection, are common protections. These terms do not change the bid price, but they change the risk the end buyer carries, and a buyer will value a bid with sensible draws above an equal bid with heavy front-loading.
Change orders
Ask how extra work will be priced: at fixed unit rates, cost plus a percentage, or by negotiation. Renovations of older houses nearly always find something. A clear change-order method keeps surprises from turning into disputes, and it lets you size the contingency with some confidence about how overruns will be charged.
See the scope of work template. WholeSellTX offers this method for general education.