How to Review a Contractor Bid Before It Goes Into the Model

A contractor bid often replaces your own estimate in the model. Before it does, check that it prices what you think it prices. This method lists criteria; it does not rate contractors.

The criteria

CriterionWhat to check
Scope matchEvery line in your scope appears, with quantities
ExclusionsWhat is explicitly not included
AllowancesItems priced as allowances (for example fixtures) and their amounts
PermitsWho pulls permits and whether fees are included
ScheduleStart date, duration and what happens if delayed
Payment termsDeposit, draws and holdback
Change ordersHow extra work is priced
Credentials and insuranceLicences for regulated trades, proof of insurance
WarrantyWhat is covered and for how long

Exclusions are where estimates fail

A low bid that excludes demolition, disposal, permits or drywall repair after plumbing work is not low. Add the excluded items at your own estimate to compare bids fairly.

Allowances

An allowance for fixtures or tile is a placeholder. If your finish level is higher, the bid will rise. Set allowances to match the finish level the ARV assumes.

Schedule as a cost

A bid that starts in six weeks adds six weeks of holding cost. Convert it to money and add it to the bid when comparing.

Regulated trades

In Texas, electricians and plumbers are licensed by state bodies, and some HVAC work requires licensing. Check the relevant licence for those trades.

A hypothetical comparison

ItemBid ABid B
Base price38,00043,000
Excluded items at your estimate+4,5000
Start delay cost+2,7000
Comparable total45,20043,000

The apparently cheaper bid is more expensive once exclusions and delay are counted. Figures are hypothetical.

Putting it in the model

Use the comparable total, keep the contingency for unknowns, and record the bid date.

Payment terms and risk

A large upfront deposit increases risk if the contractor fails to start or finish. Draws tied to completed stages, with a holdback until final inspection, are common protections. These terms do not change the bid price, but they change the risk the end buyer carries, and a buyer will value a bid with sensible draws above an equal bid with heavy front-loading.

Change orders

Ask how extra work will be priced: at fixed unit rates, cost plus a percentage, or by negotiation. Renovations of older houses nearly always find something. A clear change-order method keeps surprises from turning into disputes, and it lets you size the contingency with some confidence about how overruns will be charged.

See the scope of work template. WholeSellTX offers this method for general education.