Self-Assessment: Ten Questions for a Repair Estimate

Before a repair estimate goes into an offer, test it with these ten questions. Each is answered yes or no, and each comes with the reason it matters and what to do if the answer is no. Use it on any estimate, including your own practice ones.

The questions

  1. Is there a written scope for every line, in units a contractor would price?

*Why:* a price without a scope cannot be checked. *If no:* write the scope first, using the walkthrough checklist.

  1. Are roof, foundation, electrical, plumbing, HVAC and sewer each addressed, even if the answer is "no work needed"?

*Why:* these are the lines that swing totals. *If no:* add each, with your evidence for its status.

  1. Does each line carry a confidence rating?

*Why:* it shows where verification effort should go. *If no:* rate them high, medium or low.

  1. Is contingency tied to the low-confidence lines, with the method written down?

*Why:* a flat percentage misprices risk. *If no:* use the contingency how-to.

  1. Are areas you could not see listed as allowances rather than zeros?

*Why:* an unseen attic is an unknown, not a sound roof. *If no:* add allowances for each.

  1. Do prices come from local bids, invoices or a calibrated list, with dates?

*Why:* remembered or out-of-area prices drift. *If no:* see the price list guide.

  1. Are permit fees and inspection time included?

*Why:* many Texas cities require permits for regulated work, which adds cost and days. *If no:* add a permit line and adjust the holding period.

  1. Has the year built been checked for era risks?

*Why:* construction era hints at drains, wiring and supply pipe problems. *If no:* read repair risk by decade.

  1. Have the two or three largest uncertain lines been seen by a contractor, inspector or engineer, or flagged as unverified?

*Why:* those lines decide whether the deal survives a bad case. *If no:* get an opinion or widen the stress case.

  1. Was the estimate built without looking at the target offer?

*Why:* working backwards from a desired number is the most common source of low estimates. *If no:* rebuild the lines independently and compare.

Reading your answers

Yes answersReadiness
9–10Ready to use, with the stress case it implies
6–8Usable for screening; fix the no answers before an offer
0–5Not ready; the total could be far off

A hypothetical review

An invented estimate of 52,000 answers no to questions 5, 7 and 9: the attic was locked, permits were not included and the old HVAC was not looked at by anyone. Adding a roof allowance, a permit line and an HVAC allowance raises the total to about 64,000, and the stress case to about 74,000. The difference reduces the maximum allowable offer one-for-one.

Why question 10 matters most

An estimate that was nudged to make a deal work fails quietly: every line looks plausible, and only the total is wrong. If you suspect this happened, ask someone else to estimate the same scope blind and compare.

This self-assessment is a general learning aid. It is not an inspection or a bid; structural and safety questions belong with licensed professionals.